[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139428,798,1,"单选题","下列建设项目投资中，属于动态投资的是（）（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设期利息",true,{"key":16,"text":17,"correct":18},"B","设备及工器具购置费",false,{"key":20,"text":21,"correct":18},"C","铺地流动资金",{"key":23,"text":24,"correct":18},"D","基本预备费","建设投资可以分为静态投资部分和动态投资部分。静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。动态投资部分，是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期价格变动引起的建设投资增加额，包括涨价预备费、建设期利息等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]