[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139424":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139424,798,2,"多选题","按照造价形成划分的建筑安装工程费用中，暂列金额主要用于（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工中可能发生的工程变更的费用",true,{"key":16,"text":17,"correct":18},"B","总承包人为配合发包人进行专业工程发包产生的服务费用",false,{"key":20,"text":21,"correct":14},"C","施工合同签订时尚未确定的工程设备采购的费用",{"key":23,"text":24,"correct":14},"D","工程施工中合同约定调整因素出现时的工程价款调整的费用",{"key":26,"text":27,"correct":18},"E","在高海拔特殊地区施工增加的费用","ACD","本题考查的是按造价形成划分的建筑安装工程费用项目组成。暂列金额：是指发包人在工程量清单中暂定并包括在工程合同价款中的一笔款项。用于施工合同签订时尚未确定或者不可预见的所需材料、工程设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的工程价款调整以及发生的索赔、现场签证确认等的费用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]