[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139282":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139282,798,2,"多选题","根据《企业会计准则第15号--建造合同》，判断成本加成合同的结果能够可靠估计，至少需同时具备的条件有( )。 (2015)",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","与合同相关的经济利益很可能流入企业",true,{"key":16,"text":17,"correct":18},"B","合同总收入能够可靠的计量",false,{"key":20,"text":21,"correct":18},"C","为完成合同尚需发生的成本能够可靠地确定",{"key":23,"text":24,"correct":18},"D","合同奖励金额能够可靠地计量",{"key":26,"text":27,"correct":14},"E","实际发生的合同成本能够清楚地区分和可靠地计量","AE","判断成本加成合同的结果能够可靠估计，需同时具备以下条件只有2个： (1)与合同相关的经济利益很可能流入企业， (2)实际发生的合同成本能够清楚地区分和可靠地计量。 Ｂ和Ｃ属于总价合同结果能够可靠估价的条件；",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]