[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139273":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139273,798,2,"多选题","如果计划在固定资产投入使用的前期提取较多的折旧，后期提取较少的折旧，适合采用的折旧方法有( )。 (2014)",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作台班法",false,{"key":16,"text":17,"correct":14},"B","行驶里程法",{"key":19,"text":20,"correct":21},"C","双倍余额递减法",true,{"key":23,"text":24,"correct":14},"D","平均年限法",{"key":26,"text":27,"correct":21},"E","年数总和法","CE","企业应当根据与固定资产有关的经济利益的预期实现方式，合理选择固定资产折方法。可选用的折旧方法包括年限平均法、工作量法、双倍余额递减法和年数总和法等。 双倍余额递减法是加速折旧的方法，是在不缩短折旧年限和不改净残率的情况下，改变固定资产折旧额在各年之间的分布，在固定资产使用前期提取较多的折旧，而在使用后期则提取较少的折旧。 采用年数总和法计提折旧，各年提取的折旧额逐年递减，因此也是一种加速折旧的方法。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]