[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139259,798,1,"单选题","施工项目间接费用计入工程合同成本的方式是（ ）。2017真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接计入主要受益对象的合同成本",false,{"key":16,"text":17,"correct":18},"B","按受益合同直接费的百分比分配计入合同成本",true,{"key":20,"text":21,"correct":14},"C","按受益合同数量平均分配计入合同成本",{"key":23,"text":24,"correct":14},"D","按受益合同金额百分比分配计入合同成本","本题考查的是成本费用的计量。间接费用一般按直接费的百分比（水电安装工程、设备安装工程按人工费的百分比），进行施工间接费的分配或者按间接费定额加权分配各合同的间接费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]