[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139258,798,1,"单选题","某装饰企业施工的M项目于2012年10月工程完工时只发生材料费36万元，项目管理人员工资8万元，企业行政管理部门发生的水电费2万元．根据现行《企业会计准则》，应计入工程成本的费用为（）万元． (2013)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","36",false,{"key":16,"text":17,"correct":14},"B","38",{"key":19,"text":20,"correct":21},"C","44",true,{"key":23,"text":24,"correct":14},"D","46","工程成本的内容包括直接费用（人工费、材料费、施工机械使用费和其他直接费）和间接费用，但不包括期间费用（企业管理费、财务费用）。 行政管理部门发生的成本费属于企业管理费用的范畴．",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]