[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139218":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139218,798,2,"多选题","技术方案经济效果评价中的计算期包括技术方案的（）（2016）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投资建设期",true,{"key":16,"text":17,"correct":14},"B","投产期",{"key":19,"text":20,"correct":21},"C","投资前策划期",false,{"key":23,"text":24,"correct":14},"D","达产期",{"key":26,"text":27,"correct":21},"E","后评价期间","ABD","计算期包括建设期和运营期，运营期包括投产期和达产期。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]