[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139216,798,1,"单选题","关于财务内部收益率的说法，正确的是（ ）。 (2014)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","财务内部收益率大于基准收益率时，技术方案在经济上可以接受",true,{"key":16,"text":17,"correct":18},"B","财务内部收益率是一个事先确定的基准折现率",false,{"key":20,"text":21,"correct":18},"C","财务内部收益率受项目外部参数的影响较大",{"key":23,"text":24,"correct":18},"D","独立方案用财务内部收益率评价与财务净现值评价，结论通常不一致","财务内部收益率是一个未知的折现率。 财务内部收益率计算出来后，与基准收益率进行比较。若 F IR R > ic，则技术方案在经济上可以接受；若 F IR R ＜ic，则技术方案在经济上应予拒绝。 FIRR的大小不受外部参数影响，完全取决于技术方案投资过程净现金流量系列的情况。 对独立常规技术方案应用FIRR评价与应用FNPV 评价均可，其结论是一致的",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]