[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139201,798,1,"单选题","某项目建设投资为9700万元（其中：建设期贷款利息700万元），全部流动资金为900万元，项目投产后正常年份的年息税前利润为950万元，则该项目的总投资收益率为（）万元。2018真题",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10.56%",false,{"key":16,"text":17,"correct":14},"B","9.79%",{"key":19,"text":20,"correct":14},"C","9.60%",{"key":22,"text":23,"correct":24},"D","8.96%",true,"本题考查的是投资收益率分析。总投资收益率=技术方案运营期内正常年份的年息税前利润或运营期内年平均息税前利润\u002F技术方案总投资×100%，其中技术方案总投资包括建设投资、建设期贷款利息和全部流动资金。即ROI=950\u002F（9700+900）×100%=8.96%。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]