[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139160,798,1,"单选题","某施工现场钢筋加工有两个方案，均不需要增加投资，采用甲方案需固定费用50万元，每吨钢筋加工的可变费用是300元；采用乙方案需固定费用90万元，每吨钢筋加工的可变费用是250元,。现场需加工钢筋1万吨，如果用折算费用法选择方案，则（ ）。 (2012)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应该选用乙方案",true,{"key":16,"text":17,"correct":18},"B","应该选用甲方案",false,{"key":20,"text":21,"correct":18},"C","甲乙两个方案在经济上均不可行",{"key":23,"text":24,"correct":18},"D","甲乙两个方案的费用相同","应该选用乙方案 甲方案折算费用=50+300*1=350（万元）；乙方案折算费用=90+250*1=340（万元），故应该选择乙方案。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]