[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139153,798,2,"多选题","（2020年真题）价值工程活动中功能评价前应完成的工作有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计方案优化",false,{"key":16,"text":17,"correct":18},"B","功能整理",true,{"key":20,"text":21,"correct":14},"C","方案创造",{"key":23,"text":24,"correct":14},"D","方案评价",{"key":26,"text":27,"correct":18},"E","功能定义","BE","P71-79",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]