[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139145":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139145,798,2,"多选题","价值工程分析阶段的工作有( )。 (2015)",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对象选择",false,{"key":16,"text":17,"correct":14},"B","方案评价",{"key":19,"text":20,"correct":21},"C","功能定义",true,{"key":23,"text":24,"correct":21},"D","功能整理",{"key":26,"text":27,"correct":21},"E","功能评价","CDE","价值工程的工作程序步骤，1准备阶段，2分析阶段，3创新阶段，4实施阶段。 价值工程分析阶段的工作有功能定义、功能整理、功能评价。从工作步骤上看，对象选择属于准备阶段，方案评价属于创新阶段，所以选择CDE。 @##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]