[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139078,798,1,"单选题","某工程钢筋加工有现场制作和外包加工两个方案，现场制作方案的固定费用12万元，每吨加工费用150元；外包加工每吨加工费用250元，则仅从经济上考虑时，现场制作方案的实用范围是钢筋总加工量在（）。 (2013)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1200吨以上",true,{"key":16,"text":17,"correct":18},"B","480吨以上",false,{"key":20,"text":21,"correct":18},"C","480-800吨之间",{"key":23,"text":24,"correct":18},"D","800-1200吨之间","本题考查的是新技术、新工艺和新材料应用方案的技术经济分析。在新技术、新工艺和新材料应用方案的经济分析中，除增量投资收益率法以外，还有折算费用法。其中，两种方案的有用成果不同时，应求出其临界产量，据以进行判断。本题的临界产量（加工量）＝120000\u002F（250－150）＝1200（吨）。因此，当总量为1200吨以上时，适用于现场加工。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]