[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139075,798,1,"单选题","某项目采用净现值指标进行敏感性分析，有关数据见下表．则各因素的敏感程度由大到小的顺序是（）。 (2013)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设投资-营业收入-经营成本",false,{"key":16,"text":17,"correct":14},"B","营业收入-经营成本-建设投资",{"key":19,"text":20,"correct":14},"C","经营成本-营业收入-建设投资",{"key":22,"text":23,"correct":24},"D","营业收入-建设投资-经营成本",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]