[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139062":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139062,798,2,"多选题","若选定静态评价指标进行技术方案敏感性分析，可以选择（ ）作为不确定性因素。 (2012)",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资额、",true,{"key":16,"text":17,"correct":18},"B","折现率",false,{"key":20,"text":21,"correct":14},"C","产品销售量",{"key":23,"text":24,"correct":14},"D","产品单价",{"key":26,"text":27,"correct":14},"E","生产成本","ACDE","根据教材中的举例，可以用利润指标来进行分析，其可以分析的因素包括投资额、产品销售量、产品单价、生产成本等。 折现率，是动态的，折现率就要考虑时间价值了。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]