[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139058":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139058,798,2,"多选题","影响国际工程投标报价决策的因素主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","评标人员组成",false,{"key":16,"text":17,"correct":18},"B","成本估算的准确性",true,{"key":20,"text":21,"correct":18},"C","风险偏好",{"key":23,"text":24,"correct":18},"D","竞争条件",{"key":26,"text":27,"correct":18},"E","市场条件","BCDE","2013年建设工程经济真题第61题 本题考查的是国际工程投标报价决策的影响因素。 影响国际工程投标报价决策的因素主要有成本估算的准确性、期望利润、市场条件、竞争程度、公司的实力与规模。此外，在投标报价决策时，还应考虑风险偏好的影响。 因此，本题正确答案为BCDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]