[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139045":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139045,798,2,"多选题","国际工程项目标价计算中，将工程量清单中所有分项工程的合价汇总，即可计算出工程的总标价，总标价包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","开办费",false,{"key":16,"text":17,"correct":14},"B","利润",{"key":19,"text":20,"correct":21},"C","分项工程合价",true,{"key":23,"text":24,"correct":21},"D","分包工程总价",{"key":26,"text":27,"correct":21},"E","暂定金额","CDE","本题主要考查了标价汇总。 将工程量清单中所有分项工程的合价汇总，即可计算出工程的总标价，计算公式如下： 总标价=分项工程合价+分包工程总价+暂定金额 综上所述，本题正确答案为CDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]