[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139038":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139038,798,1,"单选题","关于国际工程投标报价的说法，错误的是（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工企业现场管理费应作为待摊费用分摊在各项综合单价中",false,{"key":16,"text":17,"correct":14},"B","现场试验设施费作为开办费应依据招标文件决定是否单列",{"key":19,"text":20,"correct":14},"C","暂定金额由业主工程师决定是否全部或部分使用",{"key":22,"text":23,"correct":24},"D","人工费工日基价应按在工程所在国招募工人的平均日工资单价计算",true,"本题考查的国际工程投标报价的组成。对于人工费工日基价，应该分为国内出国工人和当地聘用工人分别确认，所以选项D不正确。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]