[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139035":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139035,798,1,"单选题","国际工程投标报价时，对于预计施工现场发生的办公费，正确的做法是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","作为待摊费用摊入到工程量表的各计价分项价格中",true,{"key":16,"text":17,"correct":18},"B","作为待摊费单列并计入投标总标价",false,{"key":20,"text":21,"correct":18},"C","作为开办费单列并计入投标总报价",{"key":23,"text":24,"correct":18},"D","按照其费用性质分别计入相应分项工程的人工费、材料费或机具费","本题考查的是国际工程投标报价的组成。国际工程投标报价中现场管理费、临时工程设施费、保险费、税金等是在工程量清单中没有单独列项的费用项目，需将其作为待摊费用分摊到工程量清单的各个报价分项中去。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]