[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139031,798,1,"单选题","国际工程投标报价时，在工程所在国当地采购的材料设备的预算价格应按（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标人所在国预算价格",false,{"key":16,"text":17,"correct":14},"B","材料设备出厂价格",{"key":19,"text":20,"correct":21},"C","施工现场交货价格",true,{"key":23,"text":24,"correct":14},"D","当地市场价格","2009年建设工程经济真题第34题 本题主要考查了人工、材料和施工机械基础单价计算。 材料、半成本和设备预算价格的计算应按当地采购、国内供应和从第三国采购分别计算。 在工程所在国当地采购的材料设备，其预算价格应为施工现场交货价格。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]