[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139024":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139024,798,2,"多选题","国际工程投标报价前，对估价人员算出的暂时标价进行动态分析时要考虑的因素有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期延误的影响",true,{"key":16,"text":17,"correct":18},"B","分项工程量变化的影响",false,{"key":20,"text":21,"correct":18},"C","地质勘察资料错误的影响",{"key":23,"text":24,"correct":14},"D","物价和工资上涨的影响",{"key":26,"text":27,"correct":14},"E","汇率，货款利率变化的影响","ADE","2012年建设工程经济真题第62题 本题主要考查了国际工程投标报价的动态分析。 标价的动态分析是假定某些因素发生变化，测算标价的变化幅度，特别是这些变化对目标利润的影响。该项分析类似于项目投资的敏感性分析，主要考虑工期延误、物价和工资上涨、以及其他可变因素（如汇率、贷款利率、政策法规）的变化的影响。因此，ADE项正确，BC项错误。 综上所述，本题正确答案为ADE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]