[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139023,798,1,"单选题","国际工程投标报价的动态分析要考虑的因素之一是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标价结构的合理性",false,{"key":16,"text":17,"correct":14},"B","统计计算汇总数据",{"key":19,"text":20,"correct":21},"C","工期延误的影响",true,{"key":23,"text":24,"correct":14},"D","单位工程价格及用工、用料的合理性","本题的考点是国际工程投标报价的动态分析。 国际工程投标报价的动态分析主要考虑工期延误、物价和工资上涨以及其他可变因素的影响。 综上所述，本题的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]