[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139021":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139021,798,1,"单选题","国际工程投标中，投标人做出最终报价前应对估算人员算出的暂时标价进行对比分析，其目的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从宏观上把握标价的合理性",true,{"key":16,"text":17,"correct":18},"B","分析报价的竞争力",false,{"key":20,"text":21,"correct":18},"C","预测报价的利润水平",{"key":23,"text":24,"correct":18},"D","检查标价计算是否存在错误","2010年建设工程经济真题第59题 本题主要考查了国际工程投标价的分析方法。 在计算出分项工程综合单价，编出单价汇总表后，在工程估价人员算出的暂时标价的基础上，应对其进行全面的评估与分析，探讨投标报价的经济合理性，从而做出最终报价决策。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]