[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139012,798,1,"单选题","国际工程项目的价格构成比例中，材料部分约占（ ）左右的比重。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10%～20%",false,{"key":16,"text":17,"correct":14},"B","20%～30%",{"key":19,"text":20,"correct":14},"C","30%～40%",{"key":22,"text":23,"correct":24},"D","30%～50%",true,"本题主要考查生产要素与分包工程询价 。 国际工程项目的价格构成比例中，材料部分约占30%~50%的比重。 综上所述，本题D项正确，ABC项错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]