[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139007,798,1,"单选题","根据《建设工程施工合同(示范文本)》,下列可能引起合同解除的事件中,属于发包人违约的情形是（ ）。2018年",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因发包人所在国发生动乱导致合同无法履行连续超过100天",false,{"key":16,"text":17,"correct":14},"B","因罕见暴雨导致合同无法履行连续超过了20天",{"key":19,"text":20,"correct":14},"C","承包人未按进度计划及时完成合同约定工作",{"key":22,"text":23,"correct":24},"D","因发包人原因未能在计划开工日期前7天下达开工通知",true,"在合同履行过程中发生的下列情形，属于发包人违约：(1)因发包人原因未能在计划开工日期前7天内下达开工通知的；(2)因发包人原因未能按合同约定支付合同价款的；（3）发包人违反约定，自行实施被取消的工 作或转由他人实施的；（4）发包人提供的材料、工程设备的规格、数量或质量不符合合同约定，或因发包 人原因导致交货日期延误或交货地点变更等情况的；（5）因发包人违反合同约定造成暂停施工的；（6）发包人无正当理由没有在约定期限内发出复工指示，导致承包人无法复工的；（7）发包人明确表示或者以其行为表明不履行合同主要义务的；（8）发包人未能按照合同约定履行其他义务的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]