[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138982,798,1,"单选题","(2014真题)某工程承包合同总额为9000万元，主要材料及构件所占比重为60%，工程预付款为合同总额的20%，则工程预付款起扣点为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1800",false,{"key":16,"text":17,"correct":14},"B","3600",{"key":19,"text":20,"correct":14},"C","5400",{"key":22,"text":23,"correct":24},"D","6000",true,"起扣点=承包工程合同总额-工程预付款数额\u002F主要材料及构件所占比重=9000-9000*20%\u002F60%=6000（万元）。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]