[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138975,798,1,"单选题","因修改设计导致现场停工而引起施工索赔时，承包商自有施工机械的索赔费用宜按机械（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","租赁费",false,{"key":16,"text":17,"correct":14},"B","台班费",{"key":19,"text":20,"correct":21},"C","折旧费",true,{"key":23,"text":24,"correct":14},"D","大修理费","2012年建设工程经济真题第46题 本题主要考查了索赔的方法。 因窝工引起的设备费索赔，当施工机械属于施工企业自有时，按照机械折旧费计算索赔费用；当施工机械是施工企业从外部租赁时，索赔费用的标准按照租赁费计算。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]