[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138974":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":21},1138974,798,1,"单选题","某工程项目预付款120万元，合同约定：每月进度款按结算价的80%支付；每月支付安全文明施工费20万元；预付款从开工的第4个月起分3个月等额扣回，开工后前6个月结算价如下表，则第5个月应支付的款项为（ ）万元。( 2015真题 )",[11,14,16,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D","本题考查的进度款。5月份进度款=220×80%+20-120÷3=156万元。",{"id":6,"name":23,"category":24,"favorite":25},"一建建设工程经济","建筑工程",0]