[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138970,798,1,"单选题","某工程合同总额为2000万元，工程预付款为400万元，主要材料、构件所占比重为50%，则当工程完成（ ）万元时，本项工程预付款开始起扣。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1200",true,{"key":16,"text":17,"correct":18},"B","800",false,{"key":20,"text":21,"correct":18},"C","400",{"key":23,"text":24,"correct":18},"D","1000","本题主要考查了工程预付款的支付和抵扣。 起扣点的计算公式： 式中，T表示起扣点，P表示承包工程合同总额，M表示工程预付款数额，N表示主要材料、构件所占比重 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]