[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138968":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138968,798,1,"单选题","FIDIC施工合同条件下，工程量清单以外项目的保留金限额一般为合同总造价的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",true,{"key":16,"text":17,"correct":18},"B","10%",false,{"key":20,"text":21,"correct":18},"C","15%",{"key":23,"text":24,"correct":18},"D","20%","本题主要考查了FIDIC施工合同条件下建筑安装工程费用的结算。 保留金是为了确保在施工阶段，或在缺陷责任期间，由于承包人未能履行合同义务，由业主（或工程师）指定他人完成应由承包人承担的工作所发生的费用，保留金的限额一般为合同总价的5%。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]