[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138965,798,1,"单选题","根据《建设工程价款结算暂行办法》，建设工程承发包双方未在合同中对工程进度款支付时间、支付比例等作约定的，发包人应该在批准工程进度款支付申请的（ ）天内，向承包人支付规定比例范围内的工程进度款。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":14},"C","56",{"key":22,"text":23,"correct":24},"D","14",true,"2012年建设工程经济真题第20题 本题主要考查了工程计量与进度款支付。 当承发包双方未在合同中对工程进度款支付申请的核对时间以及工程进度款支付时间、支付比例做约定时，根据《建设工程价款结算暂行办法》的相关规定办理：发包人应在批准工程进度款支付申请的14天内，向承包人按不低于计量工程价款的60%，不高于计量工程价款的90%向承包人支付工程进度款。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]