[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138954,798,1,"单选题","根据《建设工程施工合同（建设工程施工合同（示范文本）》（GF-2013-0201）承包人采购材料和工程设备的，应在合同中约定主要材料、工程设备价格变化的范围或幅度；当没有约定，且材料、工程设备单价变化超过（ ）时，超过部分的价格应按照价格指数调整法或造价信息差额调整法计算调整材料、工程设备费。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%",false,{"key":16,"text":17,"correct":18},"B","5%",true,{"key":20,"text":21,"correct":14},"C","4%",{"key":23,"text":24,"correct":14},"D","3%","本题考查的是物价变化。承包人采购材料和工程设备的，应在合同中约定主要材料、工程设备价格变化的范围或幅度；当没有约定，且材料、工程设备单价变化超过5%时，超过部分的价格应按照价格指数调整法或造价信息差额调整法计算调整材料、工程设备费。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]