[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138952,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500—2013），施工过程中发生的计日工，应按照（ ）计价。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已标价工程量清单中的计日工单价",true,{"key":16,"text":17,"correct":18},"B","计日工发生时承包人提出的综合单价",false,{"key":20,"text":21,"correct":18},"C","计日工发生当月市场人工工资单价",{"key":23,"text":24,"correct":18},"D","计日工发生当月造价管理部门发布的人工指导价","本题考查的是计日工。计日工应按招标工程量清单中列出的项目根据工程特点和有关计价依据确定综合单价计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]