[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138946,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），采用清单计价的某分部分项工程，招标控制价的综合单价为350元，承包人投标报价的综合单价为300元。该工程投标报价总的下浮率为5%。结算时，该分部分项工程工程量比清单工程量增加了16%，且合同未确定综合单价调整方法，则对该综合单价的正确处理方式是（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整为257元",false,{"key":16,"text":17,"correct":14},"B","调整为282.63元",{"key":19,"text":20,"correct":21},"C","不做任何调整",true,{"key":23,"text":24,"correct":14},"D","调整为345元","本题考查的是工程量偏差。350×（1-5%）×（1-16%）=279.3元＜300元，未超过最低限值，因此该综合单价不做调整。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]