[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138944,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013），关于合同工期的说法正确的是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人要求合同工程提前竣工的，应承担承包人由此增加的提前竣工费用",true,{"key":16,"text":17,"correct":18},"B","招标人压缩的工期天数不得超过定额工期的30%",false,{"key":20,"text":21,"correct":18},"C","招标人压缩的工期天数超过定额工期的20%但不超过30%时，不额外支付赶工费用",{"key":23,"text":24,"correct":18},"D","工程实施过程中，发包人要求合同工程提前竣工的，承包人必须采取加快工程进度的措施","本题考查的是提前竣工（赶工补偿）引起的价格调整。选项B，招标人压缩的工期天数，不得超过定额工期的20%；选项C，超过20%，则应在招标文件中明示增加赶工费用；选项D，工程实施过程中，发包人要求合同工程提前竣工的，应征得承包人同意后与承包人商定采取加快工程进度的措施，并应修订合同工程进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]