[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138940,798,1,"单选题","某独立土方工程，根据《建设工程工程量清单佳佳规范》（GB50500—2013），签订了固定单价合同，招标工程量为3000m3，承包人标书中土方工程报价为55元m3。合同约定：当实际工程量超过估计工程量15%时，超过部分工程量单价调整为50元\u002Fm3。工程结束时实际完成并经监理确认的土方工程为4500 m3 ，则土方工程总价为（ ）元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","242250",true,{"key":16,"text":17,"correct":18},"B","240000",false,{"key":20,"text":21,"correct":18},"C","247500",{"key":23,"text":24,"correct":18},"D","225000","本题考查的是工程量偏差引起的价款调整。土方工程总价=3000×（1+15%）×55+[4500-3000×（1+15%）]×50=242250元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]