[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138937,798,1,"单选题","招标工程以投标截止日前28天，非招标工程以合同签订前28天前为基准日，其后国家的法律、法规、规章和政策发生变化影响工程造价的，应按省级或行业建设主管部门或其授权的工程造价管理机构发布的规定调整（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标控制价",false,{"key":16,"text":17,"correct":14},"B","投标报价",{"key":19,"text":20,"correct":14},"C","综合单价",{"key":22,"text":23,"correct":24},"D","合同价款",true,"本题考查的是工程价款调整的方法。 根据《建设工程工程量清单计价规范》有关工程价款调整的规定，招标工程以投标截止日前28天前为基准日，其后国家的法律、法规、规章和政策发生变化影响工程造价的，应按省级或行业建设主管部门或其授权的工程造价管理机构发布的规定调整合同价款。 综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]