[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138932,798,1,"单选题","工程量清单计划格式中的任何内容不得随意删除或涂改，投标人应填报工程量清单计价格中列明的所有需要填报的单价和合价，如未填报的单价和合价，则（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","招标人应要求投标人及时补充",false,{"key":16,"text":17,"correct":14},"B","投标人可以在中标后提出索赔",{"key":19,"text":20,"correct":21},"C","招标人可认为此项费用包含在工程量清单的其他单价和合价中",true,{"key":23,"text":24,"correct":14},"D","投标人应该在开标之前补充","本题主要考查了计价表格使用规定。 工程量清单与计价表中列明的所有需要填写的单价和合价，投标人均应填写，未填写的单价和合价，视为此项费用已包含在工程量清单的其他单价和合价中。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]