[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138930,798,1,"单选题","投标单位的投标报价应按招标单位提供的工程量清单的每一单项计算填写单价、合价，在开标后发现投标单位没有填写单价、合价的项目，则（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","允许投标单位补充填写",false,{"key":16,"text":17,"correct":14},"B","视为废标",{"key":19,"text":20,"correct":14},"C","由招标人退回投标书",{"key":22,"text":23,"correct":24},"D","认为此费用已包括在工程量清单的其他单价或合价中",true,"本题主要考查了计价表格使用规定。 工程量淸单与计价表中列明的所有需要填写的单价和合价，投标人均应填写，未填写的单价和合价，视为此项费用已包含在工程量淸单的其他单价和合价中。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]