[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138929":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138929,798,1,"单选题","某工程采用工程量清单招标，评标时发现甲投标人的分部分项工程量清单计价表中，有一项未填报综合单价与合价，则视为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标人漏项，招标人应要求甲投标人予以补充",false,{"key":16,"text":17,"correct":14},"B","此分部分项工程在施工中不需要做",{"key":19,"text":20,"correct":21},"C","此项费用已包含在工程量清单的其他单价和合价中",true,{"key":23,"text":24,"correct":14},"D","甲投标人的投标为废标","2011年建设工程经济真题第18题 本题主要考查了计价表格使用规定。 工程量清单与计价表中列明的所有需要填写的单价和合价，投标人均应填写，未填写的单价和合价，视为此项费用已包含在工程量清单的其他单价和合价中。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]