[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138928,798,1,"单选题","（2020年真题）单价合同在执行过程中,发现招标工程量清单中出现工程量偏差引起工程量增加，则该合同工程量应按（ ）计量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件中所附的施工图纸的工程量",false,{"key":16,"text":17,"correct":18},"B","承包人在履行合同义务中完成的工程量",true,{"key":20,"text":21,"correct":14},"C","承包人提交的已完工程量报告中的数量",{"key":23,"text":24,"correct":14},"D","原招标工程量清单中的工程量","P260-262 施工中进行工程量计量时，当发现招标工程量清单中出现缺项、工程量偏差,或因工程变更引起工程量增减时，应按承包人在履行合同义务中完成的工程量计量。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]