[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138924":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138924,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013），关于单价合同计量的说法，正确的是（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人为保证施工质量超出施工图纸范围实施的工程量，应该予以计量",false,{"key":16,"text":17,"correct":14},"B","承包人收到计量的通知后不派人参加计量，则发包人的计量结果无效",{"key":19,"text":20,"correct":21},"C","发包人应在计量前24小时通知承包人，无论承包人是否参加，计量结果有效",true,{"key":23,"text":24,"correct":14},"D","发包人可以在任何方便的时候计量，计量结果有效","本题考查的是单价合同的计量。选项A，按承包人在履行合同义务中完成的工程量计量；选项B，承包人收到通知后不派人参加计量，视为认可发包人的计量核实结果；选项D，发包人不按照约定时间通知承包人，致使承包人未能派人参加计量，计量核实结果无效。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]