[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138919,798,1,"单选题","(2014真题)采用清单计价的某分部分项工程，招标控制的综合单价为320元，投标报价的综合单价为265元，该工程投标报价下浮率为5%，结算时，该分部分项工程工程量比清单量增加了18%，且合同未确定综合单价调整方法，则综合单价的处理方式是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","上浮18%",false,{"key":16,"text":17,"correct":14},"B","下调5%",{"key":19,"text":20,"correct":14},"C","调整为292.5元",{"key":22,"text":23,"correct":24},"D","可不调整",true,"《建设工程工程量清单计价规范》GB50500-2013规定：对于任一招标工程量清单项目，如果因工程量偏差和工程变更等原因导致工程量偏差超过15%时，可进行调整。这里所说的“可进行调整”，并非强制要求，不调整也是可以的。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]