[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138911,798,1,"单选题","根据《建设工程工程量清单计价》（GB50500-2013），已标价工程量清单中没有适用也没有类似于变更工程项目的，变更工程项目单价应由（ ）提出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",true,{"key":16,"text":17,"correct":18},"B","监理人",false,{"key":20,"text":21,"correct":18},"C","发包人",{"key":23,"text":24,"correct":18},"D","设计人","本题考查的是工程变更价款的确定方法。已标价工程量清单中没有适用也没有类似于变更工程项目的，应由承包人根据变更工程资料、计量规则和计价办法、工程造价管理机构发布的信息价格和承包人报价浮动率提出变更工程项目的单价，报发包人确认后调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]