[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138906":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138906,798,2,"多选题","(2014真题)根据《标准施工招标文件》，下列事件中，承包人向发包人既可索赔工期又可索赔费用的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人原因导致工程缺陷和损失",false,{"key":16,"text":17,"correct":18},"B","承包人遇到不利物质条件",true,{"key":20,"text":21,"correct":14},"C","发包人要求向承包人提前交付工程设备",{"key":23,"text":24,"correct":18},"D","施工过程发现文物",{"key":26,"text":27,"correct":14},"E","承包人遇到异常恶劣的气候条件","BD","选项A可索赔费用、利润；选项B可索赔工期、费用；选项C可索赔费用；选项D可索赔工期、费用；选项E可索赔工期。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]