[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138901,798,1,"单选题","下列四种情形中，适宜采用固定总价合同的工程是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期6个月，规模小且施工图设计已审查批准的办公楼工程",true,{"key":16,"text":17,"correct":18},"B","采用某种新技术且较复杂，工期5年的海底隧道工程",false,{"key":20,"text":21,"correct":18},"C","采用工程量清单计价，只有初步设计图纸，工期2年的地铁站房建设工程",{"key":23,"text":24,"correct":18},"D","特大暴雨过后的紧急抢险工程","本题考查的是合同类型的选择。合同工期较短且合同总价较低的工程，可以采用固定总价合同方式。从四个选项中看，选项B，采用某种新技术且较复杂，这个适用于成本加酬金合同；选项C，只有初步设计图纸，且采用工程量清单计价，适用于单价合同；选项D，紧急抢险工程，适用于成本加酬金合同。故此题适用于固定总价合同的是选项A，工期较短且规模小、施工图纸以审查批准。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]