[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138899":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138899,798,2,"多选题","建设工程施工合同根据合同计价方式的不同，一般可以划分为总价合同、单价合同和成本加酬金合同三种类型。具体工程项目可以选择何种合同计价形式，主要依据是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计图纸深度",true,{"key":16,"text":17,"correct":18},"B","计价方式",false,{"key":20,"text":21,"correct":14},"C","工期长短",{"key":23,"text":24,"correct":14},"D","工程规模",{"key":26,"text":27,"correct":14},"E","复杂程度","ACDE","本题主要考查了工期合同类型的选择。 具体工程项目选择何种合同计价形式，主要依据设计图纸深度、工期长短、工程规模和复杂程度进行确定。 综上所述，本题正确答案为ACDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]