[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138897,798,1,"单选题","《计价规范》中规定，对使用工程量清单计价的工程，宜采用（ ）合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价",true,{"key":16,"text":17,"correct":18},"B","固定总价",false,{"key":20,"text":21,"correct":18},"C","可调总价",{"key":23,"text":24,"correct":18},"D","成本加酬金","本题主要考查了工程合同类型的选择。 具体工程项目选择何种合同计价形式，主要依据设计图纸深度、工期长短、工程规模和复杂程度进行确定，《计价规范》中规定，对使用工程量清单计价的工程，宜采用单价合同，但并不排斥总价合同。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]