[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138896,798,1,"单选题","按照《建设工程工程量清单计价规范》规定，单价合同和总价合同均可以采用工程量清单计价，区别仅在于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计价公式不同",false,{"key":16,"text":17,"correct":14},"B","计价费用构成不一样",{"key":19,"text":20,"correct":14},"C","价款最终结算方式不一样",{"key":22,"text":23,"correct":24},"D","清单中所填写的工程量的合同约束力不同",true,"本题主要考查了工程合同类型的选择。 实践中常见的单价合同和总价合同两种主要合同形式，均可以采用工程量清单计价，其区别在于工程量清单中所填写的工程量的合同约束力不同。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]