[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138880":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138880,798,2,"多选题","工程量清单招标时，投标人编制投标报价前应认真复核工程量清单中的分部分项工程量，因为该工程量会影响（ ）。 2016",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投标总价的计算",false,{"key":16,"text":17,"correct":14},"B","结算工程量的确定",{"key":19,"text":20,"correct":21},"C","施工方法选择",true,{"key":23,"text":24,"correct":21},"D","劳动力和机具安排",{"key":26,"text":27,"correct":21},"E","投标综合单价报价","CDE","本题考查的是投标价的编制与审核。工程量的多少是选择施工方法、安排人力和机械、准备材料必须考虑的因素，自然也影响分项工程的单价，因此一定要对工程量进行复核。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]